| Old
photos of the factory |
 |
The 10,000 sq. m. (100,000 sq.ft.)
site in Centelles is now cleared (of potatoes!) and flat. January 1999. |
 |
Pedro Roquet Baucells (Production Director) checking
progress. March 1999. |
 |
The roof is on and the far wall
panels are being positioned. May 1999. |
 |
The walls, windows and floor are all complete.
Electric services etc. are being installed and the surrounding area is ready
for paving. September 1999. |
 |
A few lathes and machining centres have started to
arrive and are being installed in the machining bay. September 1999. |
 |
One of the welding robots has arrived and is being
installed. September 1999. |
 |
The assembly / test bay is being painted prior to
installation of assembly, test and painting facilities. September 1999. |
 |
The goods receiving / despatch bay -
two docks can be seen. both fitted with dock-levellers (Roquet power packs and
cylinders !). September 1999. |
|
Two large lathes making cylinder rods and tubes.
Rapid automatic part transfer. Feb 2000. |
 |
Machining centres now making pieces. Feb 2000. |
 |
The paint line being installed. Feb 2000. |
 |
A welding robot welding test pieces. Feb 2000. |
 |
Ultrasonic cleaning machines with automatic part
transfer awaiting arrival of honing machines. Feb 2000. |